TPS installed a mixture of temporary and permanent fibre optic cabling (for both indoor and outdoor purposes), with runs ranging from 200m to 2km. The company also installed varying lengths of CAT6 cables to a maximum length of 90m. In addition, multiple pieces of LAN equipment were installed into the Technology Equipment Room, consisting of core switches, patch panels, cable management and UPS with battery. Cabinets were then positioned by TPS at the designated locations, with the LAN equipment and UPS ‘racked and stacked’ within the cabinets. Cross-Connect Frames (CCF’s), AP’s, mounting brackets and IP Desk Phones were also installed with all works being tested and commissioned upon completion. The TPS team of highly-skilled engineers completed the entire schedule of works to strict timescales, providing a seamless integration of network communications equipment into the overall event infrastructure.